- Plot
- 10 marla at 250 sq ft a marla: 2,500 sq ft.
- Built area
- Each floor covers 85% of the plot; a mezzanine is half a floor, a basement one floor priced at 1.35× the grey rate.
- Materials per sq ft of grey area
- 22 bricks, 0.5 bags of cement, 2.6 cft of sand, 1.7 cft of crush and 3.4 kg of steel: a full RCC frame.
- Labour, grey structure
- Rs 620 per sq ft, RCC-heavy work with more skilled labour than a house.
- Finishing
- Rs 2,100 per sq ft at the grade you pick, plus a shutter for each 300 sq ft of ground floor.
- Services
- Elevation Rs 2,800 per sq ft of street face; lift Rs 750,000 a stop; fire fighting Rs 110 per sq ft; generator Rs 1,200,000.
- Site supervision and range
- Site supervision at 5% of the works. The range is ±8% around the middle, for soil, design and market moves.
- Build time
- Grey structure about 1.8 months a floor; finishing about a month a floor.
- Price rises
- 10% a year, only for the allowance under the payment plan. The estimate itself is at this week's rates.